Upgrades at Willow Tree were completed for ARTC’s power supply and points upgrade.
A new motor generator was successfully installed in the existing power room, which included provision of a temporary gen set, ensuring the crossing loops availability.
52 points was upgraded to M23 MkIII. The installation of new cable routes, earth loggers and power supplies was also completed.








